Run Off

Roto-Flo recognizes that a critical element of the turn key process is a successful run-off.  This is the only way to assure that the machine, application engineering and tooling will meet your production requirements.  Our run-off procedure includes the following 4 step process:

  • We perform a 20 hour continuous dry cycle of the machine to insure that the complete system is functional, integrated properly and reliable.
  • Next, we perform a 10 piece qualification run to insure that the machine, process and tooling are correct.  Only after obtaining acceptable results do we invite you to witness the statistical machine qualification process at our facility. 
  • We then perform a statistical machine qualification with your personnel at our facility.  This involves the continuous run of 30 to 300 pieces to prove that the machine and process meet your Cpk requirements.  The parts are measured and statistical analysis is performed to insure that the machine and process are capable.
  • After your machine is delivered and installed at your facility, we duplicate the machine qualification process performed at our facility.  This is the final “run-off” phase of our turn key installation